Re: [bugs] I can't edit a repetition

Hi Lukas,

There is an appointment from 18 to 21 on the attached data: testing.

I go to the 'testing' appt for editing (I assume doesn't matter the day,
any one of the four).
Type 'e' and then '2' to edit the repetition.

I keep the daily repetition, typing 'd' and then keep the frequency of 1.
Finally, there is the end date: 10/21/2019
I then edit to 10/23/2019 as I want to extend in two days.

Nothing happens.

This is on 4.5.0.

I have another computer here, and that has 4.4.0, and on that version, it
works.
I can see the appt being extended, and the content o apts file:

$ cat apts
10/18/2019 [1] {1D -> 10/23/2019} testing


While the apts on version 4.5.0 is still the original end date:

$ cat apts
10/18/2019 [1] {1D -> 10/21/2019} testing

I've been using archlinux, so this package:
https://www.archlinux.org/packages/community/x86_64/calcurse/

I hope that helps.
Fabio


On Thu, Oct 17, 2019 at 5:10 PM Lukas Fleischer <lfleischer@xxxxxxxxxxxx>
wrote:

> Dear Fabio,
>
> On Thu, 17 Oct 2019 at 05:27:38, Fabio FR wrote:
> > For instance, adding a task, with daily repetition, from 2019-10-16 to
> > 2019-10-19.
> > If I try to edit it, making to finish on 2019-10-20, it doesn't work,
> > nothing happens on the UI.
> > Then I check apts file and see that the repetition is still on
> > the 2019-10-19.
>
> Thanks for reporting this bug. Unfortunately, I cannot reproduce it.
>
> Could you please create a minimal example data file (containing just one
> appointment) and describe the exact steps to reproduce the issue
> starting from this data file? Thanks!
>
> Lukas
>
>

Links